Work is underway to realise the vision of Sea Lanes and this page offers information on the progress made to date and what to expect next.

  • All pre-commencement planning conditions have been approved
  • The coastal vegetated shingle habitat has been moved to a permanent home, enlarged and improved with additional planting, new bug hotels, a boardwalk and signage.
  • Construction of the small business units began in May 2022 and is due to be completed in Autumn 2022. To register your interest in a unit please email Ed Delandes at e.deslandes@flude.com
  • The modular 50m swimming pool is being manufactured offsite in East Anglia and shall be brought to site for construction in Autumn 2022, along with the changing rooms and plant room.

Small business units: Delivery of SIPS and construction of units

Not started
In progress
Completed

Small business units: Fit-out and handover

Not started
In progress
Completed

Swimming pool: Fit-out and handover

Not started
In progress
Completed